Applicability of ICTAD Price Fluctuation Formula for Government Funded Intelligent Building Projects

dc.contributor.authorJayaweera, SC
dc.contributor.authorPerera, BAKS
dc.contributor.authorJayasinghe, SJARS
dc.date.accessioned2015-08-20T08:05:41Z
dc.date.available2015-08-20T08:05:41Z
dc.date.issued2015-08-20
dc.description.abstractIn high inflationary situations, government fiscal policies etc., have an effect on price fluctuations in Intelligent Building (IB) projects which are funded by the Government. It can increase the cost of material, plant and labour, while increasing the risks that both the contractors and the clients have to face. The use of the ICTAD price fluctuation formula in construction projects of more than three months duration, especially those of the Government, will help to recover these unforeseen costs at least to a certain extent. The formula however has its own inherent constraints. The objective of this research is to identify these constraints and suggest solutions to overcome them. An expert survey and a case study were done towards achieving the main objective. The case studies comprised a document review and semi structured interviews. Code-based content analysis was used to identify the significant conclusions that could be made from the semi-structured interviews. The QSR. NVivo computer software was used to simplify the content analysis. The results emphasised that in the case of IB projects of the Government, there is a difference between the actual price fluctuations and the corresponding figures obtained using Institute of Training and Development (ICTAD) price fluctuation formula as the formula had its own limitations. Therefore there is a need to modify the way the ‘cost adjustment’ factor is determined in IB projects of the Government. By using reliable price indices while taking steps to improve the currently available norms, it will be possible to make available to future IB projects a better operating framework.en_US
dc.description.sponsorshipInternational Council for Research and Innovation in Building and Construction (CIB)en_US
dc.identifier.conferenceThe 4th World Construction Symposium 2015en_US
dc.identifier.departmentDepartment of Building Economics, University of Moratuwa, Sri Lankaen_US
dc.identifier.facultyEngineeringen_US
dc.identifier.pgnosp 99-108en_US
dc.identifier.placeColomboen_US
dc.identifier.proceedingSustainable Development in the Built Environment: Green Growth and Innovative Directionsen_US
dc.identifier.urihttp://dl.lib.mrt.ac.lk/handle/123/11203
dc.identifier.year2015en_US
dc.language.isoenen_US
dc.subjectICTAD Price Fluctuation Formulaen_US
dc.subjectIntelligent Building (IB)
dc.subjectPrice Fluctuation
dc.titleApplicability of ICTAD Price Fluctuation Formula for Government Funded Intelligent Building Projectsen_US
dc.typeConference-Full-texten_US